I am trying to use the scheduler in Blue Prism and followed this guide to configure everything. However, my scheduled tasks are not running (nothing is started, there is no recent activity). One of the requirements to run a schedule is to have the blue prism server service running. How do I check this?

I have attached here some screenshots of my configured scheduler. The pending status on the timetable just disappears when I do "Run (schedule) now", and a checkmark never appears. The logs are also empty with no start or end time.

Schedule

No activityTimetable

1 Answer

0 votes
by (9.5k points)

it might be because you are running the scheduler in evaluating license, You should try using it with a production license.